AGGREGATES MANAGER / April 2017 13 Cemex's Lytle Creek Plant is located in southern California in the city of Rialto. The upside of the construction proj- ect? With almost 150,000 hours of work performed over a period of 468 days, there were no injuries. How did they do that? Simple. Cemex's strategy during construction included daily tailgate talks, monthly safety meetings, spot safety audits to ensure safety, counseling of individuals who violated safety procedures, and weekly contractor-Cemex management meetings. Lytle Creek was Cemex's fi rst new sand and gravel plant built in the United States. It is automated and controlled by one operator in the central control room. It is capable of producing 1,200 tons per