Issue link: https://read.dmtmag.com/i/348131
I DA U N I V E R S A L J u l y -Au g u s t 2 0 1 4 43 NUTS & BOLTS continued from page 39 updates in the newspapers on the progress and delivery of new TBMs. e scope of work for Red Line North Underground is comprised of the design and construction of approximately 13.4 km of twin-bored tunnel, including seven underground stations, between the proposed Msheireb Underground Sta- tion and Doha Golf Course via Doha West Bay. e tunnels will be built at an average depth of 20 m below ground. Red Line South Under- ground extends from Msheireb in the North to Hamad Inter- national Airport in the South. e scope of work for Red Line South Underground includes seven underground stations and the design and construc- tion of approximately 14 km of twin-bored tunnel to be built at an average depth of 25 meters below ground. Qatar Rail, the company overseeing the construction of Qatar's integrated railways network, has received four more tunnel boring machines (TBMs) for phase one of the Doha Metro. e four TBMs – Al Mayeda, Al Khor, Lehwaila and Al Wakra – were manu- factured by Germany's Her- renknecht and will be used for the Red Line North and South Underground projects. Al Mayeda and Al Khor will be used for the Red Line North Underground. e design and build (D&B) for this project will be under- taken by a joint venture led by Italy's Salini Impregilo and comprised of South Korea's S. K. Engineering & Construc- tion Co. Ltd, and Qatar's Galfar Al Misnad Engineering & Contracting W.L.L. A total of four TBMs – Lebretha, Al Mayeda, Al Khor and Al Bidda – are already on site, ready to be assembled. ey are proposed to bore the required rail tunnels for the Red Line North project. Lehwaila and Al Wakra will be launched into service for the Red Line South Under- ground project. e D&B for this project will be under- taken by a joint venture led by the French-Qatari company QDVC and comprised of South Korea's G. S. Engineering and Construction and Qatar's Al Darwish Engineering. Five TBMs (named Lehwaila, Al Wakra, Mus- haireb, Doha and Al Zubara) will be utilized for the tun- neling on the Red Line South Underground project. Each TBM will travel a distance of 7-9 km and will take roughly two years to com- plete their respective journeys. e TBM average speed will be 12-21 m/day, depending on ground conditions. Daily exca- vation quantity will be over 600 m³, with an estimated total excavation quantity of over 5,000,000 m³. Each of the TBMs for the Doha Metro measures 7.05 m in diameter and 120 m in length. To ensure transporta- tion is successfully managed from the Doha Port to the respective construction sites, the TBMs are dismantled into smaller sections which enable easier transportation. It will take a few months to reassemble all four TBMs into complete machines, and Qatar Rail will provide regular Qatar Rail Takes Delivery of Four More TBMs Qatar Rail is awaiting the delivery of an additional 16 TBMs. ese will arrive in Qatar over the coming months, to be utilized between the Red Line North, Red Line South, Green Line and Gold Line Underground projects. e Green Line – a joint venture led by Austria's PORR Bau and comprised of KSA's Saudi Bin Laden Group and Qatar's Hamad bin Khaled Contracting – will receive six TBMs. e Gold Line – recently awarded a D&B deal to a joint venture led by Greece's Aktor SA and com- prised of India's Larsen and Toubro, Turkey's Yapi Merkezi Insat ve Sanayi Anonim Sirketi, Sezai Turkes Feyzi Akkaya Marine Construction and Qatar's Al Jaber Engi- neering – will also receive six TBMs. ● www.constructionweekonline.com, by Yamurai Zendera on Jun 4, 2014 Nuts and Bolts continued on page 49