Better Roads

October 2012

Better Roads Digital Magazine

Issue link: https://read.dmtmag.com/i/86539

Contents of this Issue

Navigation

Page 11 of 109

InCourt by Brian Morrow Winds A hurricane trumps a "no liability" clause in a delay damages case. C onstruction projects are time sensitive by nature. Owners, developers, contractors, subcontractors and material suppliers commit to a project timeline so they can realize their anticipated profits within a defined schedule. When a project is delayed, one of the risks is escalating material costs. With delays, foreseeable and unforeseeable con- ditions can lead to price increases, especially for products based on commodities such as oil. As a result, material price escalation clauses have become more prominent over the past decade. However, many contracts lack a materials escalation clause. Even without such a clause, if an owner delays a contractor's work, the first place to turn is 9a October 2012 Better Roads of Change the contract to determine whether the contractor can recover delay damages. In a recent Arizona case — Technology Construction, Inc. (TCI) v. City of Kingman, 229 Ariz. 564 (decided June 12, 2012) — the Arizona court of appeals awarded delay damages to TCI relating to the increased price of asphalt due to Hurricane Katrina, despite the lack of a materials escalation clause and a "no liability" clause in the city's favor. In July 2005, TCI contracted with city of Kingman for the construction of a railroad underpass for $5,226,722. Work on the project was scheduled for two phases. Phase 1 included a shoofly and reloca- tion of a sewer line and water line, was scheduled to begin June 1, 2005, and was to be completed by June

Articles in this issue

Archives of this issue

view archives of Better Roads - October 2012