SportsTurf

October 2014

SportsTurf provides current, practical and technical content on issues relevant to sports turf managers, including facilities managers. Most readers are athletic field managers from the professional level through parks and recreation, universities.

Issue link: http://read.dmtmag.com/i/391471

Contents of this Issue

Navigation

Page 16 of 51

tions of sand-based fields cost in the $200,000-$250,000 range. A presentation made to the city's Redevelopment Commission in the fall of 2011 confirmed the dollars for the labor and materials (sod, rootzone, warning track material), setting in motion the process of selecting the sod farm. Graff 's Turf Farm in Fort Morgan, CO was selected based on the quality of their short-cut, 100% bluegrass. A July 2012 visit to the farm to inspect the turf plot confirmed every- thing was in place for the harvesting and shipping that fall. Furthermore, consultation with our front office on limiting the number of games and events in 2013 played a key part in assuring a successful grow-in. No other baseball games were scheduled besides the TinCap's dates, and other on-field activity was restricted until the fall, giving the field almost an entire year to develop. Work began on the field the second week of September after the team made a run to the Midwest League finals, and 2 weeks before a major on-field running event the last Saturday of the month that brings more than 10,000 runners to Parkview Field. The entire oblong infield horn (created during initial field installation) was reconfigured, constructing a more traditional 95-feet arc from the mound. This meant removing large amounts of clay and sod from areas to establish the new symmetry. This work was all done by the grounds crew with a 3-ton mini-excavator and a lot of hand digging and edging. On October 1 The Motz Group moved in with their Koro Field Topmaker and began stripping and grinding the existing sod layer. The Koro conveyor shoots the pulverized material into trailers pulled by tractors to get the debris off-site. More pre-planning put in place bagged meters and traffic control devices to block off a lane of park- ing and traffic on the road adjacent to the field ramp. From there, 700 cubic yards of material was hauled away thanks to a large front loader and 30-35 dump truck loads. As the sod was stripped from infield, baseline, and warning track edges, re-working of all edges was done with hand spades by the grounds crew. This is the only chance you ever get to create a new edge, and meticulous attention and time was spent to make the root- zone, clay, warning track transition zones as perfect as possible. All 88,000 square feet of sod was stripped in 2 days. As the root- zone was exposed, 70 tons of new 92% sand, 8% peat was brought in and laser graded. The infield turf area was dropped from a .1% grade to level, and all the outfield and sidelines were laser graded to spec. At this point we were ready to sod, but . . . With an extremely high content ofpoa annua infestation in the field, the decision was made to fumigate the entire turf area before the new sod was brought in. Using Basamid (dazomet) dropped from a 36-inch drop spreader, a 10-day window was allowed to kill off any remaining poa seed or plant material. Fumigation is based on soil temperatures and moisture. Moisture causes the release of vapors which penetrate the soil particles and upon contact, kill plant matter, seeds, insects, and anything living. The higher the soil temperature, the faster it works. Because dazomet is a restricted product, application was made using a respirator and full Personal Protection Equipment (PPE) attire. Additionally, barricades and posted signs around the ballpark restricted access to the field area as gases were emitted. After a 10-day fumigation window, work resumed on October 15. Before that, an organic granular starter fertilizer (5-6-6) was applied on the exposed rootzone at a rate of 10lbs/M. The maxi-rolls of Graff 's short cut bluegrass began to arrive on flat bed trucks from Colorado, which was a 1,070 mile one-way trip! A total of 22 trucks bearing anywhere from 20-22 rolls made the hike to Fort Wayne. Assistant groundskeeper Andrew Burnette off-loaded the rolls with a skid steer and The Motz Group crew went to work, rolling out sod and pulling in seams. The TinCaps grounds crew concentrated on perfecting edges while Motz laid "the carpet." At the end of Day One, the infield and skirts were completed. After waiting on the intermittent arrival of sod trucks, it took 2 more days to finish the outfield. When all 88,000 square feet of new sod was in place, another round of granular starter fertilizer (5-6-6) went down at the same rate. A couple of days later, we began our foliar fertility with a good dose of micronutrients, potassium, and magnesium. October 22, 22 tons of DuraEdge Pro infield mix arrived for infield lasing grading. The skin and base paths were pulverized with a Blecavator, the infield mix was worked in, laser graded, and rolled. An additional load of warning track material (crushed lava rock) was distributed on the edges to bring all the new turf edges flush. Our fall granular organic program commenced two weeks later with a 21-3-7, followed by two more foliar applications in November, www.stma.org October 2014 | SportsTurf 17 A total of 22 trucks bearing anywhere from 20-22 rolls made the hike to Fort Wayne. ››

Articles in this issue

Links on this page

Archives of this issue

view archives of SportsTurf - October 2014